OK. Today’s blog
posting should have appeared in the middle of the night (based on my time
zone). But it didn’t. Here’s why:
I had a soft spot in the floor in my bedroom. Ken came and looked at it and gave me a
price, saying it was a one day job to rip up the carpet and put down a layer of
plywood over the whole floor because although only a couple of places were
soft, the whole floor was probably particle board. When particle board is used for flooring, it
isn’t just nailed into the joists, it is glued down. So it is easier to leave it in place and
cover it over with plywood. Sounded good
to me, so we arranged that he and Carl would come and start work two Fridays
ago. They did.
| Yoga Room with No Room for Yoga! |
To minimize their time on the job, I cleared all the stuff
from the horizontal surfaces and moved all the small pieces of furniture to my
yoga room. I removed and stacked the
dresser drawers in the yoga room as well, to make it easier to move the
dressers. I removed all the hanging
clothes from the (14 foot long) closet and stacked them, still on their
hangers, on the futon in the spare room.
I removed all the boxes of stuff from the closet as well. I took down the curtains, too, as I planned
to wash the windows and curtains before replacing them.
| Spare Room with No Room to Spare! |
| Living Room with No Room to Live! |
As they ripped up the carpet – which was not wet – they noticed
that the padding under the carpet appeared to be wet. It turned out that the particle board under
the padding was saturated from a leak in the pipe leading into the hot water
heater. The water heater had been
replaced about 2 years ago. At that
time, the plumber pointed out that someone had put plywood under the hot water
heater, so it had probably leaked before.
But in any case, that plywood looked good so he was not going to put
plywood down. What he didn’t say, and I
didn’t notice, is that the plywood only went under half the hot water heater…
| Wet Particle Board |
So, when, at Ken’s suggestion, I started taking pictures of
this mess for my insurance man, we noticed that the hot water heater was
leaning. The particle board under the
hot water heater was also soft. That
meant that the hot water heater had to be removed so that they could fix the
floor underneath it. Fortunately, in a
previous incarnation, Ken was a plumber, so while Carl continued to work on the
floor, Ken started the process of emptying and moving the hot water heater. We decided that the outside access to the hot
water heater was a problem and that, since he was moving it anyway, it would be
an improvement to take its enclosure wall down and replace it with a door in
the bedroom.
Since the particle board was saturated, it had to be
removed. Which meant chiseling it off
the joists in crumbly bits. The underlying
wet insulation also had to be removed.
You get the picture. This is no
longer a one-day job! At the end of day
1 they put the bed frame back in the bedroom and rehung the bedroom door as the
water heater vent was now open into the room.
They did offer to make temporary connections for the hot water heater,
but that seemed like a lot of extra work as it would have to be emptied again
to relocate it, etc. So I spent the
weekend without hot water and with the living room, yoga room, and spare room
stuffed with bedroom stuff.
They came back Monday and took away the last bit of wet
particle board that they had hoped would dry out over the weekend. It didn’t.
Next they had to replace the wet insulation. The particle board they removed had to be
replaced with plywood to make an even flooring for the next layer of plywood. The floor was also covered with a moisture
barrier in preparation for the final layer of plywood and some of the plywood
was laid. The enclosure for the water
heater was expanded into the closet which meant that the stuff on the closet
shelf had to be removed so they could cut the shelf back by a foot or so. An outside door was ordered for the water
heater closet and the closet itself was fire-rocked with a vent cover to the
outside since it is a gas hot water heater.
At the end of day 2, they returned the bed frame to the
bedroom and rehung the bedroom door as the vent was still open to both the room
and the outdoors. This time, I realized
that I needed to get munchies and nutrition bars out of the pantry before it
got blocked. Should have taken a couple
of cans of soup out, too!
Unfortunately, since this was a “one-day” job, they had
scheduled other work to “follow” and that work needed to be done. So I had a few workmen-free days before they
returned. By this time, the floor is
looking good and the sheet-rock around the water heater, too. The new door was installed. All of this meant the wallpaper (on which I
had based the choice of new carpet color) looked really bad and had to go. But it wasn’t going to be easy to paint over
it, or to rip it down. So they ended up
sheet-rocking the whole room. This is a
good thing because the drafty window frames are now more securely wrapped. (I know.
Caulking the window frames would have been cheaper…)
The new walls have been painted. Trim has been put in place and painted. The carpet guys are here now and the carpet
looks great against the new paint. Next
step will be to replace the mirrored sliding closet doors. The floor guys will do that. Then I can start to reclaim the rest of my
house by returning furniture to the bedroom!
But we’re starting week three of this project. And it’s Thanksgiving week. (At least I wasn’t planning to host
Thanksgiving here, but am going to a friend’s house.) What do you think? Will the project ever be finished? Will I regain the use of my living room? Yoga room? etc.?
So that’s why today’s post is late!
No comments:
Post a Comment